Non-Standard Construction Mortgages
Anything that is not brick or stone with a tiled roof is non-standard, and lender appetite varies more here than almost anywhere else in mortgage lending. A decline from one lender tells you very little.
- What counts as non-standard construction
- Why concrete-built homes are the hard case
- The documents that make a case work
- Where cladding and EWS1 sit in 2026
broad range of UK lenders
Momentum Financial Services Ltd · FRN 1011740
a real adviser, start to finish
rates, fees & total borrowing
Tell Us About The Property
Construction type, age, any repairs carried out and any certification. We will tell you which lenders are likely to consider it and what evidence they will want.
Mon–Fri 9am–5pm · Saturday by appointment
Enquiry Form
Tell us about your situation and we'll get back to you with tailored advice.
What Counts As Non-Standard
Standard construction means walls of brick or stone with a roof of slate or tile. Everything else is non-standard, which is a much wider category than most buyers expect.
It includes timber frame, steel frame, precast reinforced concrete, no-fines concrete, prefabricated homes, thatched roofs, listed buildings, flats above or beside commercial premises, and high-rise blocks. Some of these are entirely mainstream in practice; others substantially narrow the field.
Modern timber frame with a brick outer skin is widely accepted and often treated as close to standard, because it is how a large proportion of new homes are built. At the other end, certain designated concrete types are difficult to finance at all without specific certification. The label non-standard covers both, which is why it tells you so little on its own.
For a real example, read our case study of refinancing a Grade II listed timber barn conversion.
Concrete Homes And The PRC Question
Precast reinforced concrete houses built in the decades after the Second World War are the hardest cases, and they need to be understood specifically rather than lumped in with other non-standard types.
A number of these designs, including Airey, Cornish Unit, Woolaway, Wates, Reema, Unity and Orlit among others, were formally designated as defective under legislation in the 1980s. The concrete used was prone to deterioration around the steel reinforcement within it.
Most lenders will only consider one of these where it has been fully repaired under an approved scheme and holds a PRC certificate. The critical word is fully. A common and expensive problem arises with semi-detached pairs where only one half was repaired. The certificate must cover the whole structure, and a licensed repair that stops at the party wall is frequently declined.
If you are looking at a property of this type, establish the certification position before you offer. It is the single fact that determines whether the purchase is financeable.
The Documents That Make A Case Work
Non-standard cases are won on paperwork. The valuer needs to be able to see what has been done and by whom.
For repaired concrete properties, the PRC certificate and evidence of the scope of the repair. For any structural alteration, building regulations sign-off. For timber or steel frame, warranty documentation where the property is relatively new. For thatch, evidence of recent maintenance and the insurance position, since thatch attracts higher premiums and some insurers decline it.
A structural engineer’s report is often worth commissioning proactively where there is any doubt. It costs money before you know whether the purchase will proceed, which is uncomfortable, but a report that resolves a valuer’s concern is considerably cheaper than three declined applications.
Expect the valuation to matter more than usual. On unusual property the valuer’s opinion carries more weight because there are fewer comparables, and lenders lean on it accordingly.
Flats, Cladding And EWS1
For flats in taller blocks, external wall safety is a separate question from construction type and has its own documentation.
An EWS1 form is not a legal requirement. It is a valuation tool, requested when a valuer judges it necessary, and the criteria have been narrowed considerably since the peak. Industry data shows the proportion of flat valuations requiring one has fallen substantially, and requests are now concentrated in taller buildings and those with significant combustible material on the elevations.
Where a form exists, two things are worth checking: the date, since forms are valid for five years, and the credentials of the signatory, because forms signed by unqualified assessors have caused problems. Requirements in this area continue to develop, with an updated professional standard due to take effect later in 2026.
The practical point for a buyer is to ask early. Managing agents can take weeks to produce the documentation, and a purchase that stalls waiting for it is a common and avoidable frustration.
Read More About The Property
Construction type is one of the reasons a valuation comes back short.
Types of House Survey
Which level of survey is worth paying for, and what each one misses.
Freehold or Leasehold
Lease length, ground rent and the terms that make lenders pull out.
Right to Buy Mortgages
Using your discount as the deposit, and the lenders who accept it.
Specialist Mortgages
Cases that do not fit a high street tick box, and the lenders built for them.
PRC Homes And Why Certification Decides It
Precast reinforced concrete housing is the largest single category of non-standard construction, and the rules around it are more specific than most people expect.
Around thirty house types were formally designated as inherently defective under legislation now consolidated into Part XVI of the Housing Act 1985 — among them Airey, Orlit, Reema Hollow Panel, Tarran, Wates and Wessex. The designation existed partly to help people who had bought these homes under Right to Buy and then found them unsaleable.
PRC Homes Ltd, a subsidiary of the NHBC, licensed and certificated approved repair schemes. It closed in 1996, but its certificates remain the thing lenders look for. Homes repaired under a licensed scheme were entered on an approved register. Homes given partial repairs by local authorities generally were not, and remain effectively unmortgageable despite often looking repaired.
Two published examples show how narrow the door is. One building society lender treats PRC as not normally acceptable, but will consider it where the valuer confirms resaleability is unaffected and the property has been repaired under a PRC Homes Limited approved scheme with a ten-year guarantee. A high street bank considers repaired PRC only where the property is no more than two storeys and there is no adjacent unrepaired property.
That adjacent property rule catches people out on semi-detached and terraced PRC stock: a fully certified home can still be declined because next door was never repaired.
Timber, Steel, Thatch And Cob
Non-standard does not mean unmortgageable. It means the answer depends on the specific type, and the distinctions lenders draw are quite fine.
With timber frame, the outer skin is what matters. One high street bank, for example, accepts modern timber frame with a masonry external skin as standard, and also accepts historic hardwood timber-framed infilled properties — the black-and-white buildings of Tudor towns. What it rejects is non-standard lightweight softwood timber frame without a masonry skin. So a great many timber-framed homes are treated as entirely ordinary.
Steel frame is treated more cautiously. The same bank accepts modern steel frame with a masonry external skin where it originally carried an NHBC guarantee. A building society lender treats steel frame as not normally acceptable but will consider it where the valuer confirms resaleability and a structural engineer confirms the position — which means an extra report and an extra cost.
Thatch is more mainstream than its reputation suggests. That building society accepts thatch on pitched roofs where the property is otherwise of acceptable construction, and the high street bank lists thatched among acceptable pitched roof coverings. Insurance is usually the harder problem, not the mortgage.
Cob is accepted by the same building society at a minimum of 230mm solid.
The practical lesson is that valuer commentary carries enormous weight. In several of these cases the criteria turn on whether the valuer confirms resaleability is unaffected, which makes the choice of lender and the local evidence of comparable sales genuinely decisive.
Cladding, EWS1 And Where That Stands Now
Flats in blocks with cladding form a separate problem, and the position has moved several times.
An EWS1 form is valid for five years and covers a whole block rather than an individual flat. Under a joint lender statement of March 2022, signed by five high street banks and a large building society, lenders will lend on flats in buildings over eleven metres where an EWS1 or equivalent shows an A1, A2 or B1 rating, or where an A3 or B2 applies but there is a costed and funded remediation plan with committed start and finish dates.
A further statement in December 2022 opened three routes to lending without an EWS1 at all: a developer self-remediation commitment, inclusion in a government remediation scheme, or evidence of Building Safety Act leaseholder protections through a Leaseholder Deed of Certificate. Where none of those can be evidenced, lenders typically still expect to see an EWS1.
Two developments are worth knowing. In April 2025 lenders issued updated guidance on EWS1 forms that are over five years old or signed by an invalid signatory. And in May 2026 RICS published a second edition of its cladding valuation standard extending proportionate criteria to buildings of four storeys or fewer, taking effect on 1 November 2026.
A proposed Remediation Bill would set statutory deadlines of 2029 for buildings over eighteen metres and 2031 for those of eleven metres and above, with a duty on building owners and significant penalties. It was included in the May 2026 King’s Speech and is not yet law, despite headlines suggesting the deadlines are already in force.
What To Do Next
Non-standard cases are placeable far more often than people assume, provided the groundwork is done first.
Identify The Construction Type
Ask the agent and the seller specifically. Timber frame and repaired concrete are entirely different propositions.
Find The Certification
For concrete homes, the PRC certificate and the scope of the repair. Confirm it covers the whole structure.
Gather Building Regs Sign-Off
For any structural alteration. Missing paperwork causes as many declines as the construction itself.
Ask About Cladding Early
For flats, request the external wall documentation from the managing agent at the outset. It can take weeks.
Consider An Engineer's Report
Where there is doubt, a proactive report is cheaper than repeated declined applications.
Choose The Lender First
Appetite varies enormously. Establishing who will consider it before applying saves credit searches and time.
Buying An Unusual Property?
Tell us the construction type and what documentation exists. We will tell you which lenders will consider it and what else they will want to see.
Non-Standard Construction: Frequently Asked Questions
Can I get a mortgage on a non-standard construction property?
Often yes, but the number of lenders willing to consider it varies enormously with the specific construction type. Modern timber frame is widely accepted. Designated defective concrete types generally require full repair under an approved scheme with certification. A decline from one lender says very little about whether the case can be placed.
What is a PRC certificate?
It certifies that a precast reinforced concrete property designated as defective has been repaired under an approved scheme. Most lenders require one before they will consider lending. Crucially it must cover the whole structure, which is a common problem with semi-detached pairs where only one half was repaired.
Will I pay a higher rate on a non-standard property?
Sometimes, and you may need a larger deposit. It depends on how many lenders will consider the property. Where a specialist lender is the only realistic option, pricing usually reflects that. Where mainstream lenders will consider it, rates are often unaffected.
Do I still need an EWS1 form?
Only if the valuer requests one, and requests have fallen substantially as the criteria have narrowed. They are concentrated in taller buildings and those with significant combustible material on the elevations. If a form exists, check its date and the signatory’s credentials.
Is a thatched roof a problem for a mortgage?
It narrows the panel of lenders and it complicates insurance, which is often the harder of the two. Premiums are higher and some insurers decline thatch altogether. Evidence of recent maintenance and a firm insurance quote both help the mortgage case.
Can I get a mortgage on an Airey house?
Only if it has been repaired under a licensed scheme and certified. An unrepaired designated PRC property is effectively unmortgageable on the high street. Even certified, the panel is narrow — one high street bank, for instance, considers repaired PRC only up to two storeys and declines where an adjacent property remains unrepaired.
Do I still need an EWS1 form?
Sometimes. Since December 2022 there are three alternative routes — a developer self-remediation commitment, inclusion in a government remediation scheme, or evidence of Building Safety Act leaseholder protections. Where none of those can be evidenced, lenders usually still ask for one. Forms last five years, so check the date on any form you are shown.
Is a timber-framed house non-standard?
It depends on the type. Modern timber frame with a masonry outer skin is treated as ordinary by mainstream lenders, as are historic hardwood timber-framed buildings. It is lightweight softwood frame without a masonry skin where lenders start declining.